| SHEL has undergone a constant process of learning. And that too learns through the most effective means of education-Experience. It is the company's experience of over 24 years that has enabled it to successfully complete projects of high magnitudes. Some of the company's major achievements include: |
|
| Sl. No |
Project |
Total Qty. |
Date of LOI |
Actual date of commencement |
Major Milestones |
| |
|
|
|
|
Events |
Actual completion date / Exptd. completion month |
| |
|
|
|
|
|
|
| A) Ongoing Projects - Boiler & its Auxilaries |
|
|
|
| |
|
|
|
|
|
|
| 1 |
Malwa (600MW) |
25926 MT |
13.09.10 |
09/12/10 |
|
|
| |
|
|
|
Start of erection |
09/12/10 |
| |
|
|
|
|
DL |
30/09/11 |
| |
|
|
|
|
HT (Drainable) |
June' 12 (Plan) |
| |
|
|
|
|
HT (Non Drainable) |
Jan' 13 (Plan) |
| |
|
|
|
|
BLU |
| |
|
|
|
|
Acid cleaning |
Feb' 13 (Plan) |
| |
|
|
|
|
Steam blowing |
Mar' 13 (Plan) |
| |
|
|
|
|
Synchronization |
Apr' 13 (Plan) |
| |
|
|
|
|
Coal firing |
June' 13 (Plan) |
| 2 |
Mauda (500MW) |
34749 MT |
15.09.09
(LOA) |
20.11.09 |
|
|
| |
|
|
Start of erection |
20/11/09 |
| |
|
|
|
|
DL |
02/06/10 |
| |
|
|
|
|
HT (Drainable) |
09/04/11 |
| |
|
|
|
|
HT (Non Drainable) |
20/11/11 |
| |
|
|
|
|
BLU |
19/12/11 |
| |
|
|
|
|
Acid cleaning |
15/01/12 |
| |
|
|
|
|
Steam blowing |
Feb' 12 (Plan) |
| |
|
|
|
|
Synchronization |
Mar' 12 (Plan) |
| |
|
|
|
|
Coal firing |
Apr' 12 (Plan) |
| |
|
|
|
|
|
|
| 3 |
Rihand (500MW) |
34937 MT |
12.11.2009 |
05.02.10 |
|
|
| |
|
|
|
Start of erection |
07/02/10 |
| |
|
|
|
|
DL |
06/08/10 |
| |
|
|
|
|
HT (Drainable) |
06/07/11 |
| |
|
|
|
|
HT (Non Drainable) |
19/01/12 |
| |
|
|
|
|
BLU |
31/01/12 |
| |
|
|
|
|
Acid cleaning |
Feb' 12 (Plan) |
| |
|
|
|
|
Steam blowing |
Mar' 12 (Plan) |
| |
|
|
|
|
Synchronization |
Apr' 12 (Plan) |
| |
|
|
|
|
Coal firing |
May' 12 (Plan) |
| |
|
|
|
|
|
|
| 4 |
Vindhyachal (500MW) |
34829 MT |
12.11.2009 |
11.03.10 |
|
|
| |
|
|
|
Start of erection |
11/03/10 |
| |
|
|
|
|
DL |
30/06/10 |
| |
|
|
|
|
HT (Drainable) |
30/06/11 |
| |
|
|
|
|
HT (Non Drainable) |
30/01/12 |
| |
|
|
|
|
BLU |
10 Feb' 12 (Plan) |
| |
|
|
|
|
Acid cleaning |
Mar' 12 (Plan) |
| |
|
|
|
|
Steam blowing |
Apr' 12 (Plan) |
| |
|
|
|
|
Synchronization |
May' 12 (Plan) |
| |
|
|
|
|
Coal firing |
June' 12 (Plan) |
| 5 |
Simhadri # 4 (500 MW ) |
20848 MT |
01.09.08 |
03.10.08 |
|
|
| |
|
|
|
DL |
24/03/09 |
| |
|
|
|
|
HT (Drainable) |
31/03/10 |
| |
|
|
|
|
HT (Non Drainable) |
24/10/11 |
| |
|
|
|
|
Charging of ESP & BLU |
07/12/11 |
| |
|
|
|
|
ABU |
26/12/11 |
| |
|
` |
|
|
Steam blowing |
01/02/12 |
| |
|
|
|
|
Synchronization |
Feb' 12 (Plan) |
| |
|
|
|
|
Coal firing |
Mar' 12 (Plan) |
| |
|
|
|
|
|
|
| 6 |
Ukai (500MW) |
32241 MT |
24.03.09 |
09.06.09 |
Start of erection |
9/6/2009 |
| |
|
|
|
|
DL |
31/12/09 |
| |
|
|
|
|
HT (Drainable) |
14/10/10 |
| |
|
|
|
|
HT (Non Drainable) |
23/12/11 |
| |
|
|
|
|
BLU |
21/02/12 (Plan) |
| |
|
|
|
|
Acid cleaning |
Mar' 12 (Plan) |
| |
|
|
|
|
Steam blowing |
Apr' 12 (Plan) |
| |
|
|
|
|
Synchronization |
May' 12 (Plan) |
| |
|
|
|
|
Coal firing |
July' 12 (Plan) |
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| 7 |
Chandrapur (500MW) |
32850 MT |
29.10.2009 |
01.06.10 |
|
|
| |
|
|
|
Start of erection |
01/06/10 |
| |
|
|
|
|
DL |
29/03/11 |
| |
|
|
|
|
HT (Drainable) |
Feb' 12 (Plan) |
| |
|
|
|
|
HT (Non Drainable) |
Nov' 12 (Plan) |
| |
|
|
|
|
BLU |
| |
|
|
|
|
Acid cleaning |
Dec' 12 (Plan) |
| |
|
|
|
|
Steam blowing |
| |
|
|
|
|
Synchronization |
Jan' 13 (Plan) |
| |
|
|
|
|
Coal firing |
Mar' 13 (Plan) |
| |
|
|
|
|
|
|
| 8 |
Cuttak- KVK # (350 MW) |
12665 MT |
9/7/2011 |
12/9/2011 |
|
|
| |
|
|
|
DL |
Mar' 12 (Plan) |
| |
|
|
|
HT (Drainable) |
Nov' 12 (Plan) |
| |
|
|
|
|
BLU |
April' 13 (Plan) |
| |
|
|
|
|
Acid cleaning |
May' 13 (Plan) |
| |
|
|
|
|
Steam blowing |
| |
|
|
|
|
Synchronization |
June' 13 (Plan) |
| |
|
|
|
|
Coal firing |
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| 9 |
Harduaganj # 9 (250 MW) |
14050 MT |
18.08.08 |
7/11/2008 |
|
|
| |
|
|
|
DL |
31/03/09 |
| |
|
|
|
HT (Drainable) |
26/02/10 |
| |
|
|
|
|
BLU |
20/11/11 |
| |
|
|
|
|
Acid cleaning |
20/12/11 |
| |
|
|
|
|
Steam blowing |
Feb' 12 (Plan) |
| |
|
|
|
|
Synchronization |
Mar' 12 (Plan) |
| |
|
|
|
|
Coal firing |
| |
|
|
|
|
|
|
| B) Commissioned Projects - Boiler & its Auxilaries |
|
|
|
| |
|
|
|
|
|
|
| 1 |
Khaparkeda (500MW) |
31541 MT |
30.11.2007 |
12.02.2008 |
|
|
| |
|
|
|
Start of erection |
12/02/08 |
| |
|
|
|
|
DL |
28/11/08 |
| |
|
|
|
|
HT (Drainable) |
06/11/09 |
| |
|
|
|
|
HT (Non Drainable) |
12/09/10 |
| |
|
|
|
|
BLU |
27/10/10 |
| |
|
|
|
|
Acid cleaning |
18/11/10 |
| |
|
|
|
|
Steam blowing |
06/02/11 |
| |
|
|
|
|
Synchronization |
31/03/11 |
| |
|
|
|
|
Coal firing |
| |
|
|
|
|
Full load |
05/08/11 |
| 2 |
Bhusawal # 4 (500 MW) |
31343 MT |
06.03.2008 |
26.03.2008 |
|
|
| |
|
|
|
DL |
08/01/09 |
| |
|
|
|
|
HT (Drainable) |
31/03/10 |
| |
|
|
|
|
HT (Non Drainable) |
24/12/10 |
| |
|
|
|
|
BLU |
05/03/11 |
| |
|
|
|
|
Acid cleaning |
Mar' 11 |
| |
|
|
|
|
Steam blowing |
19/04/11 |
| |
|
|
|
|
Synchronization |
11/05/11 |
| |
|
|
|
|
Coal firing |
29/09/11 |
| |
|
|
|
|
|
|
| 3 |
Ratnagiri # 1 (300MW ) |
13092 MT |
21.05.08 |
18.06.08 |
DL |
1/11/2008 |
| |
|
|
|
HT (Drainable) |
5/6/2009 |
| |
|
|
|
|
Stator Lift |
11/5/2009 |
| |
|
|
|
|
LP TG Box up |
24/11/09 |
| |
|
|
|
|
Charging of ESP & BLU |
31/01/10 |
| |
|
|
|
|
Syncronization |
22/06/10 |
| |
|
|
|
|
Coal firing |
10/7/2010 |
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| 4 |
Ratnagiri # 3 (300 MW ) |
13092 MT |
21.05.08 |
10.11.08 |
DL |
30/04/09 |
| |
|
|
|
HT (Drainable) |
30/01/10 |
| |
|
|
|
|
Stator Lift |
Dec' 10 |
| |
|
|
|
|
LP TG Box up |
28/12/10 |
| |
|
|
|
|
Charging of ESP & BLU |
11/3/2011 |
| |
|
|
|
|
Steam blowing |
12/3/2011 |
| |
|
|
|
|
Syncronization |
30/04/11 |
| |
|
|
|
|
Coal firing |
2/5/2011 |
| |
|
|
|
|
COD |
9/5/2011 |
| 5 |
Harduaganj # 8 (250 MW) |
14050 MT |
18.08.08 |
25.08.08 |
|
|
| |
|
|
|
DL |
24/01/09 |
| |
|
|
|
|
HT (Drainable) |
20/11/09 |
| |
|
|
|
|
BLU |
24/03/11 |
| |
|
|
|
|
Acid cleaning |
06/06/11 |
| |
|
|
|
|
Steam blowing |
14/07/11 |
| |
|
|
|
|
Synchronization |
10/08/11 |
| |
|
|
|
|
coal firing |
| |
|
|
|
|
Full load |
27/09/11 |
| |
|
|
|
|
|
|
| 6 |
New Parli # 2 (250 MW) |
14658 MT |
17.11.2007 |
17.11.2007 |
|
|
| |
|
|
|
DL |
15/04/08 |
| |
|
|
|
|
HT (Drainable) |
17/12/08 |
| |
|
|
|
|
BLU |
13/07/09 |
| |
|
|
|
|
Synchronization |
12/11/09 |
| |
|
|
|
|
Coal firing |
01/01/10 |
| |
|
|
|
|
|
|
| 7 |
Paras # 2
(250 MW) |
15323 MT |
17.11.2007 |
25.11.2007 |
|
|
| |
|
|
|
DL |
15/05/08 |
| |
|
|
|
|
HT (Drainable) |
18/02/09 |
| |
|
|
|
|
BLU |
22/07/09 |
| |
|
|
|
|
Synchronization |
30/11/09 |
| |
|
|
|
|
Coal firing |
18/02/10 |
| 8 |
Bhilai #1
(250 MW) |
15384 MT |
03.01.06 |
15.02.06 |
|
|
| |
|
|
|
Start dt. |
15/02/06 |
| |
|
|
|
|
DL |
30/06/06 |
| |
|
|
|
|
HT (Drainable) |
15/04/07 |
| |
|
|
|
|
BLU |
31/12/07 |
| |
|
|
|
|
Synchronization |
20/04/08 |
| |
|
|
|
|
Coal firing |
27/12/08 |
| |
|
|
|
|
Trail operation |
31/10/09 |
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| 9 |
Raigrh # 3
(135 MW ) |
12391 MT |
25.11.08 |
09.04.09 |
DL |
23/07/09 |
| |
|
|
|
HT (Drainable) |
23/12/10 |
| |
|
|
|
|
HT (Non Drainable) |
10/5/2011 |
| |
|
|
|
|
Furnace leak test & BLU |
1/7/2011 |
| |
|
|
|
|
EDTA |
7/7/2011 |
| |
|
|
|
|
Steam blowing |
12/7/2011 |
| |
|
|
|
|
Syncronization |
5/11/2011 |
| |
|
|
|
|
Coal firing |
| |
|
|
|
|
|
|
| 10 |
Raigrh # 4 (135 MW ) |
12391 MT |
25.11.08 |
04.07.09 |
DL |
23.10.09 |
| |
|
|
|
HT (Drainable) |
8/7/2011 |
| |
|
|
|
|
HT (Non Drainable) |
4/11/2011 |
| |
|
|
|
|
Furnace leak test & BLU |
22/12/11 |
| |
|
|
|
|
EDTA |
25/12/11 |
| |
|
|
|
|
Steam blowing |
7/1/2012 |
| |
|
|
|
|
Syncronization |
19/01/12 |
| |
|
|
|
|
Coal firing |
| |
|
|
|
|
|
|
| 11 |
Mangrol # 3 (125 MW ) |
12006 MT |
25.01.2007 |
07.05.07 |
|
|
| |
|
|
|
DL |
25/08/07 |
| |
|
|
|
|
HT (Drainable) |
10/10/08 |
| |
|
|
|
|
BLU |
17/09/09 |
| |
|
|
|
|
Steam blowing |
24/10/09 |
| |
|
|
|
|
Coal firing |
26/11/09 |
| |
|
|
|
|
Synchronization |
| |
|
|
|
|
|
|
| 12 |
Barsingsar # 1 (125 MW ) |
13724 MT |
06.11.06 |
14.03.2007 |
|
|
| |
|
|
|
DL |
21/06/07 |
| |
|
|
|
|
HT (Drainable) |
11/08/08 |
| |
|
|
|
|
Charging of ESP & BLU |
15/09/09 |
| |
|
|
|
|
ABU |
21/09/09 |
| |
|
|
|
|
Steam blowing |
04/10/09 |
| |
|
|
|
|
Synchronization |
05/11/09 |
| |
|
|
|
|
Coal firing |
22/12/09 |
| |
|
|
|
|
Full load |
28/06/10 |
| |
|
|
|
|
|
|
| 13 |
Barsingsar # 2 ( 125 MW ) |
13566 MT |
06.11.06 |
04.05.2007 |
DL |
14/09/07 |
| |
|
|
|
HT (Drainable) |
01/06/09 |
| |
|
|
|
|
Charging of ESP & BLU |
20/02/10 |
| |
|
|
|
|
ABU |
03/03/10 |
| |
|
|
|
|
Steam blowing |
10/04/10 |
| |
|
|
|
|
Synchronization |
03/06/10 |
| |
|
|
|
|
Coal firing |
24/08/10 |
| |
|
|
|
|
Full load |
30/01/11 |
| |
|
|
|
|
|
|
| C) On going Projects - Civil & structure |
|
|
|
| |
|
|
|
|
|
|
| 1 |
Koradi # 8
(660 MW) |
Concreting - 167000 CuM
Structure - 20950 MT |
6/1/2010 |
21/1/2010 |
EOT Crane erection |
Aug' 11 |
| |
|
|
TG Deck Casting |
2/12/2011 |
| 2 |
Koradi # 9
(660 MW) |
|
|
EOT Crane erection |
07/02/12 (Plan) |
| |
|
|
TG Deck Casting |
15/04/12 (Plan) |
| 3 |
Koradi # 10
(660 MW) |
|
|
|
|
| |
|
|
TG Deck Casting |
Sep' 12 (Plan) |
| 4 |
DB Power# 1
(600 MW) |
Concreting - 146000 CuM
Structure - 20000 MT |
13/12/10 |
23/01/11 |
EOT Crane erection |
Oct' 11 |
| |
|
|
TG Deck Casting |
31/01/12 |
| 5 |
DB Power# 2
(600 MW) |
|
|
EOT Crane erection |
Nov' 11 |
| |
|
|
TG Deck Casting |
31/05/12 (Plan) |
| 6 |
Jhabua # 1
(600 MW) |
Concreting - 83882 CuM
Structure - 20500 MT |
20/09/10 |
14/10/10 |
EOT Crane erection |
Mar' 12 (Plan) |
| |
|
|
TG Deck Casting |
25/02/12 (Plan) |
| 7 |
Jhabua # 2
(600 MW) |
|
Yet not started |
EOT Crane erection |
|
| |
|
|
TG Deck Casting |
|
| 8 |
Parli - BOP #
(250 MW) |
Concreting - 80000 CuM
Structure - 13500 MT |
1/1/2010 |
|
EOT Crane erection |
13/11/11 |
| |
|
|
TG Deck Casting |
29/11/11 |
| 9 |
Satpura # 10
(250 MW) |
Concreting - 60000 CuM
Structure - 15500 MT |
23/10/2009 |
24/10/09 |
EOT Crane erection |
10/9/2011 |
| |
|
|
TG Deck Casting |
27/03/11 |
| 10 |
Satpura # 11
(250 MW) |
|
|
EOT Crane erection |
15/11/11 |
| |
|
|
TG Deck Casting |
20/10/11 |
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| C) On going Projects - STG work |
|
|
|
| |
|
|
|
|
|
|
| 1 |
Rihand # 5
(500 MW)
|
|
7/9/2010 |
27/09/10 |
Stator Lifting |
10/1/2011 |
| |
|
|
|
LP TG Box up |
30/01/12 |
| |
|
|
|
|
Oil flushing |
15/02/12 (Plan) |
| |
|
|
|
|
Syncronization |
Mar' 12 (Plan) |
| |
|
|
|
|
|
|
| 2 |
Rihand # 6
(500 MW)
|
|
7/9/2010 |
Yet not started |
Stator Lifting |
Mar' 12 (Plan) |
| |
|
|
|
LP TG Box up |
|
| |
|
|
|
|
Oil flushing |
|
| |
|
|
|
|
Syncronization |
|
| |
|
|
|
|
|
|
| 3 |
Butibori # 1
(300 MW) |
|
|
4/5/2011 |
Stator Lifting |
24/05/11 |
| |
|
|
|
LP TG Box up |
10/2/2012 (Plan) |
| |
|
|
|
|
Syncronization |
15/03/12 (Plan) |
| |
|
|
|
|
|
|
| 4 |
Butibori # 2
(300 MW) |
|
11/8/2010 |
Yet not started |
Stator Lifting |
|
| |
|
|
|
LP TG Box up |
|
| |
|
|
|
|
Syncronization |
|
| |
|
|
|
|
|
|
| D) Comissioned Projects - STG work |
|
|
|
| |
|
|
|
|
|
|
| 5 |
Ratnagiri # 1
(300 MW) |
|
21.05.08 |
18.06.08 |
Stator Lifting |
11/5/2009 |
| |
|
|
|
LP TG Box up |
24/11/09 |
| |
|
|
|
|
Syncronization |
22/06/10 |
| |
|
|
|
|
|
|
| 6 |
Ratnagiri # 3
(300 MW) |
|
21.05.08 |
Nov' 09 |
Stator Lifting |
Dec' 09 |
| |
|
|
|
LP TG Box up |
28/12/10 |
| |
|
|
|
|
Syncronization |
30/04/11 |
| |
|
|
|
|
|
|
| 7 |
New Parli # 2
(250 MW) |
|
|
|
Stator Lifting |
|
| |
|
|
|
LP TG Box up |
3/6/2009 |
| |
|
|
|
|
Syncronization |
12/11/2009 |
| |
|
|
|
|
|
|
| 8 |
Raigarh # 3
(135 MW) |
|
25.11.08 |
7/3/2010 |
Stator Lifting |
June' 10 |
| |
|
|
|
LP TG Box up |
15/05/11 |
| |
|
|
|
|
Syncronization |
5/11/2011 |
| |
|
|
|
|
|
|
| 9 |
Raigarh # 4
(135 MW) |
|
25.11.08 |
20/02/11 |
Stator Lifting |
Dec' 10 |
| |
|
|
|
LP TG Box up |
27/08/11 |
| |
|
|
|
|
Syncronization |
19/01/12 |
| |
|
|
|
|
|
|
|
| |
|
Successfully completed the first EPC Contract of Fuel Oil & Storage tank system of 250MW Unit-1 of Paras TPS Expansion Project, Maharashtra.
Awarded Occupational Health and Safety Management systems Certificate (OSHAS 18001:2007) by international certification services, DNV.
Involved in fast track construction JPL’s 2x250MW, Raigad Project and completed TG area structural works with an achievement of 13200MT of Fabrication & 11500MT of erection in a year.
Completed Structural & Boiler Erection works of 1x250MW, Unit-1 at Parli & Paras TPS with repeat order for Unit-2, 1x250MW.
Involved in the fast track construction of 500 MW, 7th unit at Chandrapur, Completed 8500 MT of Power House Structures in 18 months against 24 months schedule. |
|
| |
|
At NTPC Talcher (2x500 MW) Structural Work Fabrication and Erection in a single month 1947 MT 1879 MT respectively. Fabrication & Erection in a single year of 15478 MT & 13447 MT respectively.
At Suratgarh 250MW (RVUN) Structural Work, Fabrication & Erection, in a single month of 2340 MT & 1800 MT respectively. Fabrication & Erection in a single year of 9400 MT & 9100 MT respectively. Work completed to suit fast track completion of 28 months from financial closure.
At Chandrapur (500 MW) & Suratgarh (250MW) Boiler Aus. Work completed to suit fast track commissioning program.
Completion of major rehabs involving 7000 field joints of pressure parts work of repairing & reversing of economizer coils in less then 40 days at NTPC Korba. |
 |
|
| |
|
At U-2 Chandrapur STPS Completed Reheater replacement within the scheduled time of 25 days & complete total replacement of Condenser Tubes in a record time of 35 days
Completed total replacement of LTSH, Economiser Coils, HRH including Hangers, terminal and supply tubes replacement was done in a span of 25 days involving 5400 HP Joint at Tuticorin TNEB. |
|
| |