I S O   9 0 0 1 : 2 0 0 8   C o m p a n y                                                                                                                                                                                              O H S A S  1 8 0 0 1 : 2 0 0 7   C o m p a n y                                                                                                                                                                                              
About Us | Our Network | Products | Infrastructure | Investor Relations | Careers
  Milestone
SHEL has undergone a constant process of learning. And that too learns through the most effective means of education-Experience. It is the company's experience of over 24 years that has enabled it to successfully complete projects of high magnitudes. Some of the company's major achievements include:
Sl. No Project Total Qty. Date of LOI Actual date of commencement Major Milestones
          Events Actual completion date / Exptd. completion month
             
A) Ongoing Projects - Boiler & its Auxilaries      
             
1 Malwa (600MW) 25926 MT 13.09.10 09/12/10    
        Start of erection 09/12/10
          DL 30/09/11
          HT (Drainable) June' 12  (Plan)
          HT (Non Drainable) Jan' 13  (Plan)
          BLU
          Acid cleaning Feb' 13  (Plan)
          Steam blowing Mar' 13  (Plan)
          Synchronization Apr' 13  (Plan)
          Coal firing June' 13  (Plan)
2 Mauda (500MW) 34749 MT 15.09.09
(LOA)
20.11.09    
      Start of erection 20/11/09
          DL 02/06/10
          HT (Drainable) 09/04/11
          HT (Non Drainable) 20/11/11
          BLU 19/12/11
          Acid cleaning 15/01/12
          Steam blowing Feb' 12 (Plan)
          Synchronization Mar' 12 (Plan)
          Coal firing Apr' 12  (Plan)
             
3 Rihand (500MW) 34937 MT 12.11.2009 05.02.10    
        Start of erection 07/02/10
          DL 06/08/10
          HT (Drainable) 06/07/11
          HT (Non Drainable) 19/01/12
          BLU 31/01/12
          Acid cleaning Feb' 12 (Plan)
          Steam blowing Mar' 12 (Plan)
          Synchronization Apr' 12 (Plan)
          Coal firing May' 12 (Plan)
             
4 Vindhyachal (500MW) 34829 MT 12.11.2009 11.03.10    
        Start of erection 11/03/10
          DL 30/06/10
          HT (Drainable) 30/06/11
          HT (Non Drainable) 30/01/12
          BLU 10 Feb' 12 (Plan)
          Acid cleaning Mar' 12 (Plan)
          Steam blowing Apr' 12 (Plan)
          Synchronization May' 12 (Plan)
          Coal firing June' 12 (Plan)
5 Simhadri # 4    (500 MW ) 20848 MT 01.09.08 03.10.08    
        DL 24/03/09
          HT (Drainable) 31/03/10
          HT (Non Drainable) 24/10/11
          Charging of ESP & BLU 07/12/11
          ABU 26/12/11
    `     Steam blowing 01/02/12
          Synchronization Feb' 12 (Plan)
          Coal firing Mar' 12 (Plan)
             
6 Ukai (500MW) 32241 MT 24.03.09 09.06.09 Start of erection 9/6/2009
          DL 31/12/09
          HT (Drainable) 14/10/10
          HT (Non Drainable) 23/12/11
          BLU 21/02/12 (Plan)
          Acid cleaning Mar' 12 (Plan)
          Steam blowing Apr' 12 (Plan)
          Synchronization May' 12 (Plan)
          Coal firing July' 12 (Plan)
             
             
7 Chandrapur (500MW) 32850 MT 29.10.2009 01.06.10    
        Start of erection 01/06/10
          DL 29/03/11
          HT (Drainable) Feb' 12 (Plan)
          HT (Non Drainable) Nov' 12 (Plan)
          BLU
          Acid cleaning Dec' 12 (Plan)
          Steam blowing
          Synchronization Jan' 13  (Plan)
          Coal firing Mar' 13  (Plan)
             
8 Cuttak- KVK #  (350 MW) 12665 MT 9/7/2011 12/9/2011    
        DL Mar' 12 (Plan)
        HT (Drainable) Nov' 12 (Plan)
          BLU April' 13 (Plan)
          Acid cleaning May' 13 (Plan)
          Steam blowing
          Synchronization June' 13 (Plan)
          Coal firing
             
             
9 Harduaganj # 9 (250 MW) 14050 MT 18.08.08 7/11/2008    
        DL 31/03/09
        HT (Drainable)  26/02/10
          BLU 20/11/11
          Acid cleaning 20/12/11
          Steam blowing Feb' 12 (Plan)
          Synchronization Mar' 12 (Plan)
          Coal firing
             
B) Commissioned Projects - Boiler & its Auxilaries      
             
1 Khaparkeda (500MW) 31541 MT 30.11.2007 12.02.2008    
        Start of erection 12/02/08
          DL 28/11/08
          HT (Drainable) 06/11/09
          HT (Non Drainable) 12/09/10
          BLU 27/10/10
          Acid cleaning 18/11/10
          Steam blowing 06/02/11
          Synchronization 31/03/11
          Coal firing
          Full load 05/08/11
2 Bhusawal # 4  (500 MW) 31343 MT 06.03.2008 26.03.2008    
        DL 08/01/09
          HT (Drainable) 31/03/10
          HT (Non Drainable) 24/12/10
          BLU 05/03/11
          Acid cleaning Mar' 11
          Steam blowing 19/04/11
          Synchronization 11/05/11
          Coal firing 29/09/11
             
3 Ratnagiri # 1 (300MW ) 13092 MT 21.05.08 18.06.08 DL 1/11/2008
        HT (Drainable) 5/6/2009
          Stator Lift 11/5/2009
          LP TG Box up 24/11/09
          Charging of ESP & BLU  31/01/10
          Syncronization 22/06/10
          Coal firing 10/7/2010
             
             
4 Ratnagiri # 3    (300 MW ) 13092 MT 21.05.08 10.11.08 DL 30/04/09
        HT (Drainable)  30/01/10
          Stator Lift Dec' 10
          LP TG Box up 28/12/10
          Charging of ESP & BLU 11/3/2011
          Steam blowing 12/3/2011
          Syncronization 30/04/11
          Coal firing 2/5/2011
          COD 9/5/2011
5 Harduaganj # 8  (250 MW) 14050 MT 18.08.08 25.08.08    
        DL 24/01/09
          HT (Drainable) 20/11/09
          BLU 24/03/11
          Acid cleaning 06/06/11
          Steam blowing 14/07/11
          Synchronization  10/08/11
          coal firing
          Full load 27/09/11
             
6 New Parli # 2 (250 MW) 14658 MT 17.11.2007 17.11.2007    
        DL 15/04/08
          HT (Drainable) 17/12/08
          BLU 13/07/09
          Synchronization 12/11/09
          Coal firing 01/01/10
             
7 Paras  # 2
(250 MW)
15323 MT 17.11.2007 25.11.2007    
        DL 15/05/08
          HT (Drainable) 18/02/09
          BLU 22/07/09
          Synchronization 30/11/09
          Coal firing 18/02/10
8 Bhilai  #1
(250 MW)
15384 MT 03.01.06 15.02.06    
        Start dt. 15/02/06
          DL 30/06/06
          HT (Drainable) 15/04/07
          BLU 31/12/07
          Synchronization 20/04/08
          Coal firing 27/12/08
          Trail operation 31/10/09
             
             
9 Raigrh # 3
(135 MW )
12391 MT 25.11.08 09.04.09 DL 23/07/09
        HT (Drainable) 23/12/10
          HT (Non Drainable) 10/5/2011
          Furnace leak test & BLU 1/7/2011
          EDTA 7/7/2011
          Steam blowing 12/7/2011
          Syncronization  5/11/2011
          Coal firing
             
10 Raigrh # 4   (135 MW ) 12391 MT 25.11.08 04.07.09 DL 23.10.09
        HT (Drainable) 8/7/2011
          HT (Non Drainable) 4/11/2011
          Furnace leak test & BLU 22/12/11
          EDTA 25/12/11
          Steam blowing 7/1/2012
          Syncronization  19/01/12
          Coal firing
             
11 Mangrol # 3 (125 MW ) 12006 MT 25.01.2007 07.05.07    
        DL 25/08/07
          HT (Drainable) 10/10/08
          BLU 17/09/09
          Steam blowing 24/10/09
          Coal firing 26/11/09
          Synchronization
             
12 Barsingsar # 1 (125 MW ) 13724 MT 06.11.06 14.03.2007    
        DL 21/06/07
          HT (Drainable) 11/08/08
          Charging of ESP & BLU 15/09/09
          ABU 21/09/09
          Steam blowing 04/10/09
          Synchronization 05/11/09
          Coal firing 22/12/09
          Full load 28/06/10
             
13 Barsingsar # 2 ( 125 MW ) 13566  MT 06.11.06 04.05.2007 DL 14/09/07
        HT (Drainable) 01/06/09
          Charging of ESP & BLU 20/02/10
          ABU 03/03/10
          Steam blowing 10/04/10
          Synchronization 03/06/10
          Coal firing 24/08/10
          Full load 30/01/11
             
C) On going Projects - Civil & structure      
             
1 Koradi # 8
(660 MW)
Concreting - 167000 CuM
Structure - 20950 MT
6/1/2010 21/1/2010 EOT Crane erection Aug' 11
      TG Deck Casting 2/12/2011
2 Koradi # 9
(660 MW)
    EOT Crane erection 07/02/12 (Plan)
      TG Deck Casting 15/04/12 (Plan)
3 Koradi # 10
(660 MW)
       
      TG Deck Casting Sep' 12 (Plan)
4 DB Power# 1
(600 MW)
Concreting - 146000 CuM
Structure - 20000 MT
13/12/10 23/01/11 EOT Crane erection Oct' 11 
      TG Deck Casting 31/01/12
5 DB Power# 2
(600 MW)
    EOT Crane erection Nov' 11
      TG Deck Casting 31/05/12 (Plan)
6 Jhabua # 1
(600 MW)
Concreting - 83882 CuM
Structure - 20500 MT
20/09/10 14/10/10 EOT Crane erection Mar' 12 (Plan)
      TG Deck Casting 25/02/12 (Plan)
7 Jhabua # 2
(600 MW)
  Yet not started EOT Crane erection  
      TG Deck Casting  
8 Parli - BOP #
(250 MW)
Concreting - 80000 CuM
Structure - 13500 MT
1/1/2010   EOT Crane erection 13/11/11
      TG Deck Casting 29/11/11
9 Satpura # 10
(250 MW)
Concreting - 60000 CuM
Structure - 15500 MT
23/10/2009 24/10/09 EOT Crane erection 10/9/2011
      TG Deck Casting 27/03/11
10 Satpura # 11
(250 MW)
    EOT Crane erection 15/11/11
      TG Deck Casting 20/10/11
             
             
C) On going Projects - STG work      
             
1 Rihand # 5
(500 MW)
  7/9/2010 27/09/10 Stator Lifting 10/1/2011
        LP TG Box up 30/01/12
          Oil flushing 15/02/12 (Plan)
          Syncronization Mar' 12 (Plan)
             
2 Rihand # 6
(500 MW)
  7/9/2010 Yet not started Stator Lifting Mar' 12 (Plan)
        LP TG Box up  
          Oil flushing  
          Syncronization  
             
3 Butibori # 1
(300 MW)
    4/5/2011 Stator Lifting 24/05/11
        LP TG Box up 10/2/2012 (Plan)
          Syncronization 15/03/12 (Plan)
             
4 Butibori # 2
(300 MW)
  11/8/2010 Yet not started Stator Lifting  
        LP TG Box up  
          Syncronization  
             
D) Comissioned Projects - STG work      
             
5 Ratnagiri # 1
(300 MW)
  21.05.08 18.06.08 Stator Lifting 11/5/2009
        LP TG Box up 24/11/09
          Syncronization 22/06/10
             
6 Ratnagiri # 3
(300 MW)
  21.05.08 Nov' 09 Stator Lifting Dec' 09
        LP TG Box up 28/12/10
          Syncronization 30/04/11
             
7 New Parli  # 2
(250 MW)
      Stator Lifting  
        LP TG Box up 3/6/2009
          Syncronization 12/11/2009
             
8 Raigarh  # 3
(135 MW)
  25.11.08 7/3/2010 Stator Lifting June' 10
        LP TG Box up 15/05/11
          Syncronization 5/11/2011
             
9 Raigarh  # 4
(135 MW)
  25.11.08 20/02/11 Stator Lifting Dec' 10
        LP TG Box up 27/08/11
          Syncronization 19/01/12
             
 
  • Successfully completed the first EPC Contract of Fuel Oil & Storage tank system of 250MW Unit-1 of Paras TPS Expansion Project, Maharashtra.
  • Awarded Occupational Health and Safety Management systems Certificate (OSHAS 18001:2007) by international certification services, DNV.
  • Involved in fast track construction JPL’s 2x250MW, Raigad Project and completed TG area structural works with an achievement of 13200MT of Fabrication & 11500MT of erection in a year.
  • Completed Structural & Boiler Erection works of 1x250MW, Unit-1 at Parli & Paras TPS with repeat order for Unit-2, 1x250MW.
  • Involved in the fast track construction of 500 MW, 7th unit at Chandrapur, Completed 8500 MT of Power House Structures in 18 months against 24 months schedule.
  •  
  • At NTPC Talcher (2x500 MW) Structural Work Fabrication and Erection in a single month 1947 MT 1879 MT respectively. Fabrication & Erection in a single year of 15478 MT & 13447 MT respectively.
  • At Suratgarh 250MW (RVUN) Structural Work, Fabrication & Erection, in a single month of 2340 MT & 1800 MT respectively. Fabrication & Erection in a single year of 9400 MT & 9100 MT respectively. Work completed to suit     fast track completion of 28 months from financial closure.
  • At Chandrapur (500 MW) & Suratgarh (250MW) Boiler Aus. Work completed to suit fast track commissioning program.
  • Completion of major rehabs involving 7000 field joints of pressure parts work of repairing & reversing of economizer coils in less then 40 days at NTPC Korba.
  •  
  • At U-2 Chandrapur STPS Completed Reheater replacement within the scheduled time of 25 days & complete total replacement of Condenser Tubes in a record time of 35 days

  • Completed total replacement of LTSH, Economiser Coils, HRH including Hangers, terminal and supply tubes replacement was done in a span of 25 days involving 5400 HP Joint at Tuticorin TNEB.
  •  