I S O   9 0 0 1 : 2 0 0 0   C o m p a n y                                                                                                                                                                                              O H S A S  1 8 0 0 1 : 2 0 0 7   C o m p a n y                                                                                                                                                                                              
About Us | Our Network | Products | Infrastructure | Investor Relations | Careers
  Milestone
SHEL has undergone a constant process of learning. And that too learns through the most effective means of education-Experience. It is the company's experience of over 24 years that has enabled it to successfully complete projects of high magnitudes. Some of the company's major achievements include:
Month wise major event to be achieved in 09-10.
Date : 04.12.2009
Sl. No.
Name of Site
Unit Capacity
Package
Major Events
Remarks
Apr' 09 (Achieved)
May'09 (Achieved)
June'08 (Achieved)
July'09 (Achieved)
Aug'09 (Achieved)
Sep'09 (Achieved)
Oct'09 (Achieved)
Nov' 09 (Achieved)
Dec'09 (Plan)
Jan'10 (Plan)
Fab' 10 (Plan)
Mar' 10 (Plan)
Post pond events
A ) Boiler / str.  Sites
1 Amarkantak 210MW Structure   Handing over)                        
2 Barsingsar-I 125MW Boiler           15.09.09 (BLU)   05.11.09 (Syncronization)   (CF) Handing over      
3 Barsingsar-II 125MW Boiler     01.06.09 (HT)             (BLU)   syncronization (CF) & Handing over  
4 Bhusawal 500MW Boiler                     (HT) (BLU)    
5 Chabra - I 250MW Structure             02.10.09 (CF)       Handing over      
6 Chabra - II 250MW Structure                 (CF)     Handing over    
7 Dadri # 5 500MW ESP       23.07.09 (BLU)         27.12.09 (CF)     Handing over    
8 Dadri # 6 500MW ESP                   (BLU)   (CF)    
9 Hissar-I 600MW Structure                 07.12.09 (CF)          
10 Hissar - II 600MW Structure                   Handing over        
11 Harduaganj # 8 250MW Boiler               20.11.09 (HT)       (BLU) syncronization  
12 Harduaganj # 9 250MW Boiler                   (HT)   (BLU)    
13 Khaparkheda 500MW Boiler               06.11.09 (HT)   22.01.09 (BLU)   syncronization    
14 Kota (TATA) 195MW Structure         04.08.09 (CF)       Handing over          
15 Mangrol -III 125MW Boiler       19.07.09 (BLU)       29.11.09 (Syncronization)   (CF)   Handing over    
16 Mauda 500MW Boiler                     DL      
17 Paras 250MW Boiler       22.07.09 (BLU)       30.11.09 (Syncronization)   30.01.09 (CF)        
18 Parli 250MW Boiler       13.07.09 (BLU)       12.11.09 (Syncronization)   15.01.09 (CF)        
19 Raigad # 3 135MW Boiler       23.07.09 (DL)             (HT)      
20 Raigad # 4 135MW Boiler             23.10.09 (DL)              
21 Ratnagiri # 1 300MW Boiler     05.06.09 (HT)           31.12.09 (BLU)   syncronization (CF)    
22 Ratnagiri # 3 300MW Boiler 30.04.09 (DL)               15.12.0 (HT)   (BLU)   syncronization & (CF)  
23 Simhadri  500MW Boiler                     (HT)      
24 Ukai 500MW Boiler                 30.12.09 (DL)          
      Total Events 01 01 02 05 01 01 02 06 08 08 08 10 05 58
B) TG Sites
1 Parli 250MW TG     03.06.09 (LP TG Boxup               Trail ope ration Handing over    
2 Ratnagiri # 1 300MW TG   11.05.09 (Stator lifting)           24.11.09 LP TG Box up     Trail ope ration Handing over    
3 Ratnagiri # 3 300MW TG                 Stator lifting          
4 Raigad # 3 135MW TG                       Stator lifting    
5 Raigad # 4 135MW TG                            
Total Events 01 01         01 01 00 02 03   09
 
Note : 
Total Events 67 DL Drum Lifting
Achieved up to Sep' 09 22 HT Hydro test
    BLU Boiler light up
Balance 45   Event achieved
 
  • Successfully completed the first EPC Contract of Fuel Oil & Storage tank system of 250MW Unit-1 of Paras TPS Expansion Project, Maharashtra.
  • Awarded Occupational Health and Safety Management systems Certificate (OSHAS 18001:2007) by international certification services, DNV.
  • Involved in fast track construction JPL’s 2x250MW, Raigad Project and completed TG area structural works with an achievement of 13200MT of Fabrication & 11500MT of erection in a year.
  • Completed Structural & Boiler Erection works of 1x250MW, Unit-1 at Parli & Paras TPS with repeat order for Unit-2, 1x250MW.
  • Involved in the fast track construction of 500 MW, 7th unit at Chandrapur, Completed 8500 MT of Power House Structures in 18 months against 24 months schedule.
  •  
  • At NTPC Talcher (2x500 MW) Structural Work Fabrication and Erection in a single month 1947 MT 1879 MT respectively. Fabrication & Erection in a single year of 15478 MT & 13447 MT respectively.
  • At Suratgarh 250MW (RVUN) Structural Work, Fabrication & Erection, in a single month of 2340 MT & 1800 MT respectively. Fabrication & Erection in a single year of 9400 MT & 9100 MT respectively. Work completed to suit     fast track completion of 28 months from financial closure.
  • At Chandrapur (500 MW) & Suratgarh (250MW) Boiler Aus. Work completed to suit fast track commissioning program.
  • Completion of major rehabs involving 7000 field joints of pressure parts work of repairing & reversing of economizer coils in less then 40 days at NTPC Korba.
  •  
  • At U-2 Chandrapur STPS Completed Reheater replacement within the scheduled time of 25 days & complete total replacement of Condenser Tubes in a record time of 35 days

  • Completed total replacement of LTSH, Economiser Coils, HRH including Hangers, terminal and supply tubes replacement was done in a span of 25 days involving 5400 HP Joint at Tuticorin TNEB.
  •  