| SHEL has undergone a constant process of learning. And that too learns through the most effective means of education-Experience. It is the company's experience of over 24 years that has enabled it to successfully complete projects of high magnitudes. Some of the company's major achievements include: |
|
| Month wise major event to be achieved in 09-10. |
Date : 04.12.2009 |
Sl. No. |
Name of Site |
Unit Capacity |
Package |
Major Events |
Remarks |
Apr' 09 (Achieved) |
May'09 (Achieved) |
June'08 (Achieved) |
July'09 (Achieved) |
Aug'09 (Achieved) |
Sep'09 (Achieved) |
Oct'09 (Achieved) |
Nov' 09 (Achieved) |
Dec'09 (Plan) |
Jan'10 (Plan) |
Fab' 10 (Plan) |
Mar' 10 (Plan) |
Post pond events |
| A ) Boiler / str. Sites |
| 1 |
Amarkantak |
210MW |
Structure |
|
Handing over) |
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Barsingsar-I |
125MW |
Boiler |
|
|
|
|
|
15.09.09 (BLU) |
|
05.11.09 (Syncronization) |
|
(CF) |
Handing over |
|
|
|
| 3 |
Barsingsar-II |
125MW |
Boiler |
|
|
01.06.09 (HT) |
|
|
|
|
|
|
(BLU) |
|
syncronization |
(CF) & Handing over |
|
| 4 |
Bhusawal |
500MW |
Boiler |
|
|
|
|
|
|
|
|
|
|
(HT) |
(BLU) |
|
|
| 5 |
Chabra - I |
250MW |
Structure |
|
|
|
|
|
|
02.10.09 (CF) |
|
|
|
Handing over |
|
|
|
| 6 |
Chabra - II |
250MW |
Structure |
|
|
|
|
|
|
|
|
(CF) |
|
|
Handing over |
|
|
| 7 |
Dadri # 5 |
500MW |
ESP |
|
|
|
23.07.09 (BLU) |
|
|
|
|
27.12.09 (CF) |
|
|
Handing over |
|
|
| 8 |
Dadri # 6 |
500MW |
ESP |
|
|
|
|
|
|
|
|
|
(BLU) |
|
(CF) |
|
|
| 9 |
Hissar-I |
600MW |
Structure |
|
|
|
|
|
|
|
|
07.12.09 (CF) |
|
|
|
|
|
| 10 |
Hissar - II |
600MW |
Structure |
|
|
|
|
|
|
|
|
|
Handing over |
|
|
|
|
| 11 |
Harduaganj # 8 |
250MW |
Boiler |
|
|
|
|
|
|
|
20.11.09 (HT) |
|
|
|
(BLU) |
syncronization |
|
| 12 |
Harduaganj # 9 |
250MW |
Boiler |
|
|
|
|
|
|
|
|
|
(HT) |
|
(BLU) |
|
|
| 13 |
Khaparkheda |
500MW |
Boiler |
|
|
|
|
|
|
|
06.11.09 (HT) |
|
22.01.09 (BLU) |
|
syncronization |
|
|
| 14 |
Kota (TATA) |
195MW |
Structure |
|
|
|
|
04.08.09 (CF) |
|
|
|
Handing over |
|
|
|
|
|
| 15 |
Mangrol -III |
125MW |
Boiler |
|
|
|
19.07.09 (BLU) |
|
|
|
29.11.09 (Syncronization) |
|
(CF) |
|
Handing over |
|
|
| 16 |
Mauda |
500MW |
Boiler |
|
|
|
|
|
|
|
|
|
|
DL |
|
|
|
| 17 |
Paras |
250MW |
Boiler |
|
|
|
22.07.09 (BLU) |
|
|
|
30.11.09 (Syncronization) |
|
30.01.09 (CF) |
|
|
|
|
| 18 |
Parli |
250MW |
Boiler |
|
|
|
13.07.09 (BLU) |
|
|
|
12.11.09 (Syncronization) |
|
15.01.09 (CF) |
|
|
|
|
| 19 |
Raigad # 3 |
135MW |
Boiler |
|
|
|
23.07.09 (DL) |
|
|
|
|
|
|
(HT) |
|
|
|
| 20 |
Raigad # 4 |
135MW |
Boiler |
|
|
|
|
|
|
23.10.09 (DL) |
|
|
|
|
|
|
|
| 21 |
Ratnagiri # 1 |
300MW |
Boiler |
|
|
05.06.09 (HT) |
|
|
|
|
|
31.12.09 (BLU) |
|
syncronization |
(CF) |
|
|
| 22 |
Ratnagiri # 3 |
300MW |
Boiler |
30.04.09 (DL) |
|
|
|
|
|
|
|
15.12.0 (HT) |
|
(BLU) |
|
syncronization & (CF) |
|
| 23 |
Simhadri |
500MW |
Boiler |
|
|
|
|
|
|
|
|
|
|
(HT) |
|
|
|
| 24 |
Ukai |
500MW |
Boiler |
|
|
|
|
|
|
|
|
30.12.09 (DL) |
|
|
|
|
|
| |
|
|
Total Events |
01 |
01 |
02 |
05 |
01 |
01 |
02 |
06 |
08 |
08 |
08 |
10 |
05 |
58 |
| B) TG Sites |
| 1 |
Parli |
250MW |
TG |
|
|
03.06.09 (LP TG Boxup |
|
|
|
|
|
|
|
Trail ope ration |
Handing over |
|
|
| 2 |
Ratnagiri # 1 |
300MW |
TG |
|
11.05.09 (Stator lifting) |
|
|
|
|
|
24.11.09 LP TG Box up |
|
|
Trail ope ration |
Handing over |
|
|
| 3 |
Ratnagiri # 3 |
300MW |
TG |
|
|
|
|
|
|
|
|
Stator lifting |
|
|
|
|
|
| 4 |
Raigad # 3 |
135MW |
TG |
|
|
|
|
|
|
|
|
|
|
|
Stator lifting |
|
|
| 5 |
Raigad # 4 |
135MW |
TG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Events |
01 |
01 |
|
|
|
|
01 |
01 |
00 |
02 |
03 |
|
09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note : |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Events |
67 |
|
DL |
Drum Lifting |
|
|
|
|
|
|
|
|
|
|
|
|
Achieved up to Sep' 09 |
22 |
|
HT |
Hydro test |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
BLU |
Boiler light up |
|
|
|
|
|
|
|
|
|
|
|
|
Balance |
45 |
|
|
Event achieved |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
Successfully completed the first EPC Contract of Fuel Oil & Storage tank system of 250MW Unit-1 of Paras TPS Expansion Project, Maharashtra.
Awarded Occupational Health and Safety Management systems Certificate (OSHAS 18001:2007) by international certification services, DNV.
Involved in fast track construction JPL’s 2x250MW, Raigad Project and completed TG area structural works with an achievement of 13200MT of Fabrication & 11500MT of erection in a year.
Completed Structural & Boiler Erection works of 1x250MW, Unit-1 at Parli & Paras TPS with repeat order for Unit-2, 1x250MW.
Involved in the fast track construction of 500 MW, 7th unit at Chandrapur, Completed 8500 MT of Power House Structures in 18 months against 24 months schedule. |
|
| |
|
At NTPC Talcher (2x500 MW) Structural Work Fabrication and Erection in a single month 1947 MT 1879 MT respectively. Fabrication & Erection in a single year of 15478 MT & 13447 MT respectively.
At Suratgarh 250MW (RVUN) Structural Work, Fabrication & Erection, in a single month of 2340 MT & 1800 MT respectively. Fabrication & Erection in a single year of 9400 MT & 9100 MT respectively. Work completed to suit fast track completion of 28 months from financial closure.
At Chandrapur (500 MW) & Suratgarh (250MW) Boiler Aus. Work completed to suit fast track commissioning program.
Completion of major rehabs involving 7000 field joints of pressure parts work of repairing & reversing of economizer coils in less then 40 days at NTPC Korba. |
 |
|
| |
|
At U-2 Chandrapur STPS Completed Reheater replacement within the scheduled time of 25 days & complete total replacement of Condenser Tubes in a record time of 35 days
Completed total replacement of LTSH, Economiser Coils, HRH including Hangers, terminal and supply tubes replacement was done in a span of 25 days involving 5400 HP Joint at Tuticorin TNEB. |
|
| |