| Capabilities |
|
| |
| Ability to mobilize 150 High-Pressure welders, meeting IBR and ASME Standards for Quality Boilers and more than 1500 LP welders for piping works.
Key skills in Pressure parts, Critical Piping & Large Diameter Piping works.
Ability to Fabricate and Erect 100,000 MT of structures in a year
Ability to complete RCC works to the tune of 25000 to 30000 Cum in a year.
Ability to complete 85,000 field weld joints in a year for Boilers and Critical piping work
Ability to complete 250 MW Boiler works in 16-18 months
Ability to complete more than 70,000 High-Pressure joints in Overhauling and maintenance works in a year
Achieve 2,500 - 3,500 MT of peak fabrication & erection work in a month per site
In-house capabilities for RT, UT, MPT.
Strong asset base with more than 215 cranes in the capacity from 8 Ton to 230 Ton and over 1550 welding equipments.
Engineering drawing detailing by state of the art software (Stru Cad of ACE CAD Software system, UK) and dedicated team for the same. |
 |
|
 |
|
| EXPERIENCE |
|
| Description |
Quantity |
| Structural Fabrication & Erection. |
3,75,000 MT |
| Boiler & Equipment Erection |
1,35,000 MT |
| Ash Slurry Piping |
1,40,000 RM |
| Critical Piping |
12,500 MT |
| R&M (Replacement of Major Pressure Parts & Modification in (500 MW & 210 MW) Units |
17,500 MW |
| Major overhaul of 210/500 MW Boilers |
15,000MW |
| Concreting |
2,30,000 M3 |
| Earth work Excavation |
4,75,000 M3 |
| Radiographic Testing (RT) |
12,50,000 cms |
| Magnetic Particle Testing (MPT) |
2,55,000 cms |
| Ultrasonic Testing (UT) |
3,95,000 cms |
| Liquid Penetrant Testing (LPT) |
7,80,000 cms |
| Thickness Survey Measurement |
6,75,000 Spots |
|
|
| |
|
|
|